Cost to build a house
Enter the finished floor area and a construction cost per square foot. The calculator starts from the national average in the NAHB Cost of Constructing a Home survey, splits the total by stage of construction, and shows a low and high end at a margin you set.
Cost to build a house
Finished living space, which is what the survey divides by: not the garage or an unfinished basement.
NAHB's 2024 survey averaged $162 per ft² nationally. Local costs vary a lot: type your builder's figure if you have one.
Your own assumption, not the survey's: it reports one national average, not a range.
In the survey, construction was 64.4% of a new home's sale price. The finished lot (13.7%), financing, overhead, marketing, sales commission and the builder's profit made up the rest.
Likely construction cost
$243,000
- Low
- $207k
- High
- $279k
- Survey home (2024)
- 2,647 ft²
Low, likely, high
Where the money goes
- Interior finishes$58,67224%
- Major systems rough-ins$46,71419%
- Framing$40,28017%
- Exterior finishes$32,63513%
- Foundations$25,39310%
- Site work$18,5678%
- Final steps$15,7256%
- Other$5,0142%
NAHB cost per ft², by survey
The formula
- Finished floor area: the heated living space, in ft² or m². The survey divides its cost by finished area, so a garage, porch or unfinished basement is not in it.
- Times the cost per square foot: the default is the survey's national average, $162 per ft² ($1,741 per m²) of finished floor. Use a local builder's figure when you have one.
- Low and high: the likely cost less and plus a margin you choose. The survey publishes one national average, not a range, so the margin is your own assumption and the chart says so.
- By stage: the likely cost split in the survey's proportions: interior finishes 24.1%, major systems rough-ins 19.2%, framing 16.6%, exterior finishes 13.4%, foundations 10.5%, site work 7.6%, final steps 6.5% and other 2.1%.
The source, and what it leaves out
Every default comes from the National Association of Home Builders' Cost of Constructing a Home-2024 (Eric Lynch, NAHB Economics, January 20, 2025; summary on Eye on Housing, January 23, 2025). It is the latest edition: NAHB runs the survey every two or three years. Builders reported a typical home of 2,647 ft² with an average construction cost of $428,215, about $162 per ft². That cost includes labour, subcontractors and materials, plus permit, impact, water and sewer fees and architecture and engineering (under site work). It excludes the finished lot, financing, the builder's overhead and general expenses, marketing, sales commission and profit, which together made up 35.6% of the average sale price of $665,298. The results are national averages from 41 usable builder responses; NAHB says the sample is too small to break down by region and that it is not a tool for pricing a particular house in a particular place. Finish level and region therefore have no multiplier here: type your own cost per square foot instead.Worked example
A 1,500 ft² single-storey house at the survey's $162 per ft²: 1,500 × 162 = $243,000 of construction. With a ±15% margin, $206,550 to $279,450. Split as the survey splits its average home: interior finishes about $58,670, major systems rough-ins $46,710, framing $40,280, exterior finishes $32,640, foundations $25,390, site work $18,570, final steps $15,730 and other $5,010. The land, the loan and a builder's overhead and profit come on top.
| Finished area | Likely | Low (−15%) | High (+15%) |
|---|---|---|---|
| 1,000 ft² | $162,000 | $137,700 | $186,300 |
| 1,500 ft² | $243,000 | $206,550 | $279,450 |
| 2,000 ft² | $324,000 | $275,400 | $372,600 |
| 2,500 ft² | $405,000 | $344,250 | $465,750 |
| 3,000 ft² | $486,000 | $413,100 | $558,900 |
In metric, 140 m² at $1,741 per m² is about $243,700. The survey is of US builders in US dollars; outside the US, use a local cost per square metre.
Why your number will differ
- Place. Labour, land and to some extent materials cost different amounts from one area to the next, which is why the survey is a national average and not a local price.
- The house itself. A two-storey house puts the same floor area on a smaller foundation and roof; a complex shape adds corners, valleys and labour. Finishes (cabinets, flooring, fixtures) are the largest stage and the most variable.
- Time. The survey's cost per ft² was $114 in 2019, $153 in 2022 and $162 in 2024, not adjusted for inflation. A price from a past year needs bringing forward.
- What is counted. A builder's quote usually includes overhead and profit; the survey's construction cost does not.
Price it from a plan
The finished area is the number that matters most, and it is easy to get wrong. Draw the house in FloorGen and it measures every room; the Schedules and budget panel (in the account menu) lists floor, wall and opening quantities and multiplies them by rates you enter. See how to calculate square footage for what counts as finished area, and materials estimate from a floor plan for a worked house.
Open the 1,500 sq ft starter house Opens a 3-bedroom, 2-bath, 50 × 30 ft house in the FloorGen studio, free and without an account. Change the rooms, then read the finished area off the plan.
Questions
How much does it cost to build a house per square foot?
How much does it cost to build a 2,000 sq ft house?
Does the cost include the land?
Which stage of building a house costs the most?
Why is there no finish-level or state option?
Get the finished area right first.